1. Amrapali , vide letter dated 23 Mar 10, has intimated that instalment number 11 of Rs 2,38,562.50 .
2. As per Agreement, instalment number 11 was to be paid only on completion of Flooring. However, during my visit to the above mentioned site on 21 Mar 10, I found that Flooring work has not started. Further, internal plaster has also not been completed, which was linked with completion of instalment number 10.
3. Also, marketing representative at Amrapali was very pessimistic about the progress. He did not arrange the site visit and told me to speak with the security guard to take me around; while he was reclining in the Sofa. I had to plead repeatedly for the site visit and only after major altercation, I was successful in visiting the work-site. Also, I observed that the pace of work at the site was very slow and hardly any manpower was being employed. This proves that the Project is heading towards further time-overruns, and Amrapali is totally non-committal.
4. In view of the above, I am doubtful of the progress of the Project.
5. I requested Amrapali to provide me proof of completion of Flooring to enable me to make the payment linked with this stage of completion. However, the same has not been provided. In these circumstances, I should not be responsible for any delay in payment and associated interest.